Whatshot

2026
All
September
2025
All
November
All
2024
All
June
All
April
All
2023
All
March
All
2022
All
2021
All
2020
All
March
All
February
All
2019
All
December
All
November
All
October
All
September
All
August
All
July
All
June
All
May
All
April
All
March
All
February
All
2018
All
December
All
November
All
October
All
September
All
August
All
July
All
June
All
May
All
April
All
March
All
February
All
2017
All
December
All
November
All
October
All
September
All
August
All
July
All
June
All
May
All
April
All
March
All
February
All
January
All
2016
All
December
All
November
All
October
All
September
All
August
All
July
All
June
All
May
All
April
All
March
All
February
All
January
All
2015
All
December
All
November
All
October
All
September
All
August
All
July
All
June
All
May
All
DHS
April
All
March
All
February
All
January
All
2014
All
December
All
November
All
October
All
September
All
August
All
July
All
June
All
KZN
May
All
April
All
March
All
February
All
January
All
2013
All
December
All
November
All
October
All
September
All
August
All
July
All
June
All
May
All
April
All
March
All
February
All
January
All
2012
All
December
All
November
All
October
All
September
All
August
All
July
All

Berth Deepening Mega Project Out to Tender

Berth Deepening Mega Project Out to Tender

Date: 2016-12-23
Transnet National Ports Authority is pleased to announce that its mega project to deepen and lengthen berths at Durban Container Terminal (DCT): Pier 2 has reached a key milestone and the multi-billion rand Main Marine Construction Works package will go out to tender in December 2016.

This follows the two environmental approvals secured from the Department of Environmental Affairs (DEA) last year for marine and landside works. The tender process for the landside works will follow at a later stage.

TNPA Chief Executive, Richard Vallihu, said: "The continued investment in infrastructure and modernisation of our flagship Port of Durban is pivotal in meeting the ever-increasing demands of the maritime industry, in particular the ever-increasing size of container vessels pulling into our ports."

The DCT: Pier 2 Berths 203 to 205 reconstruction, deepening and lengthening project forms an integral part of Transnet's Market Demand Strategy which is in its 5th year and aims to enable the effective, efficient and economic functioning of an integrated port system to promote economic growth.

The increased size of container vessels calling the Port of Durban has resulted in DCT: Pier 2 berths now operating beyond their original design specification in regards to water depth.

DCT: Pier 2 handles approximately 65% of the total containerised cargo of South Africa and is the main link to the country's industrial and economic hub, Gauteng. It is estimated that the demand through the Port of Durban is expected to grow from 2.5 million TEUs (Twenty-Foot Equivalent Unit) to 3.5 million TEUs, over the next 10 years.

The overall R7 billion project aims to improve efficiencies and reduce costs for vessels calling at the port by deepening Berths 203, 204 and 205, as well as the basin and approach channel, from 12.8m to 16.5m. The effective berthing length will be increased from 914m to 1210m, to safely accommodate the simultaneous berthing of three Super Post Panamax vessels of 350m in length and draft of 14.5m.

Currently Super Post Panamax vessels take up two berths on the North Quay which decreases port capacity. In addition, large vessels requiring a deeper draft than 12.2m can only enter the channel at high tide, resulting in delays. Increasing the draft will enable vessels to enter at any time reducing the queue of vessels waiting at anchorage to enter the port.

The procurement sourcing strategy for all the project packages is clearly defined, including focus areas for Supplier Development (SD), B-BBEE Improvement Plans and Local Content (LC) that advance transformation and build capacity among Black Owned (BO), Black Woman Owned (BWO) and Youth Owned (YO) Companies.